February 15, 2018

Quick update as residential installations near!!

Happy post-Snowmageddon!!! A big shout out to the City street department for handling the snow this past week!!! OK, a quick update on FiberNet… We are continuing to work with our construction partners to get a few neighborhoods complete to the point where we can...

January 31, 2018

State of the FiberNet Union

Greetings my fellow FiberNet fans!!  The state of our FiberNet build is getting stronger every day!! We are continuing to build out the network with our construction partners getting closer and closer every day to residential installations!! Some work on that front has already begun,...

December 29, 2017

Year-end review

In only 9 short months, the Marshall FiberNet team has managed to accomplish a tremendous amount of success.  Starting in April, we have managed to design and begin construction of a state-of-the-art Fiber to the Premise(FTTP) network.  This effort involved the extensive site analysis and...

December 1, 2017

A quick update

Happy Friday (at time of writing) everybody!! A quick update on the process and the status of Marshall’s most exciting development (FiberNet)!! SO the process we go through to get customers online goes like this:  We go through a thorough and rigorous design/analysis phase first,...

November 10, 2017

Construction continues!!

Hey there FiberNet fans!! Ever wonder what it looks like up on top of the water towers? Here is a sneak peek at some of the technology that is primarily communications based, and a bird’s eye view (partial) of our beautiful city!!! On behalf of...

October 23, 2017

Progress notes...

Ok, on behalf of Team FiberNet, we thought it was time to put out a quick update on the status of the FiberNet project. The project is proceeding in a series of stages, many building off of the previous steps in the process.  Right now,...

September 26, 2017

Backbone nearing completion!!

Marshall FiberNet is pleased to pass on the news that Phase One “the backbone” is nearing completion!! Phase Two will be the first residential build-out.  We are working on finalizing construction drawings, and preparing post-bid contracts for council to approve. The hurricanes that hit Houston...

August 17, 2017

Backbone construction moving right along!!!

This is what we want to see!!!  This shows our construction contractor Earthcomm installing the fiber optic cable as part of the “Backbone” construction phase.  Exciting times are here and it’s only going to get better!!! Stay tuned for further developments and updates!!!

July 24, 2017

FiberNet construction begins in earnest!!!

Dateline Marshall, Construction has officially started!!  The first stretches of “strand” (the steel wire cable that supports the Fiber Optic cable) are being installed today up on Brewer St and Old 27 N.!!!!!! The Marshall FiberNet team encourages you to take extra driving precautions in...

July 7, 2017

Crews swinging into action!!!

That’s right!! Crews are beginning the “Make-Ready” process.  This stage of work prepares the poles and existing cable configurations to allow our construction contractors to work efficiently and safely on the “Backbone” path around the city.  TRANSLATION: It’s happening!!! FiberNet is coming soon!!! Stay tuned...